What is the maximum overload protection size, based on 430.32(A)(1), for a 480-Volt, 25-horsepower, 3-phase motor marked with a 1.15 service factor and a nameplate current of 32 amperes? Assume this selection will permit the motor to start and the sizing per 430.32(C) is not warranted.

Enhance your coding skills with the Code Standards and Practices Level 3 Test. Access well-crafted questions, insightful explanations, and progress tracking to master this exam. Prepare effectively for your Level 3 certification with our comprehensive study materials!

Multiple Choice

What is the maximum overload protection size, based on 430.32(A)(1), for a 480-Volt, 25-horsepower, 3-phase motor marked with a 1.15 service factor and a nameplate current of 32 amperes? Assume this selection will permit the motor to start and the sizing per 430.32(C) is not warranted.

Explanation:
In motor circuits, overload protection must be sized not to exceed 125% of the motor’s full-load current. The motor’s full-load current on the nameplate is 32 A, so 1.25 × 32 = 40 A. The largest standard protection size that stays within this limit is 40 A, making it the maximum overload protection size. The 44.8 A option would exceed the limit, while smaller options are allowed but not the maximum. The service factor (1.15) indicates the motor can handle a bit more than rated briefly, but it doesn’t change the 125% limit for overload protection in this scenario, and we’re not applying 430.32(C) here.

In motor circuits, overload protection must be sized not to exceed 125% of the motor’s full-load current. The motor’s full-load current on the nameplate is 32 A, so 1.25 × 32 = 40 A. The largest standard protection size that stays within this limit is 40 A, making it the maximum overload protection size. The 44.8 A option would exceed the limit, while smaller options are allowed but not the maximum. The service factor (1.15) indicates the motor can handle a bit more than rated briefly, but it doesn’t change the 125% limit for overload protection in this scenario, and we’re not applying 430.32(C) here.